Since about 7 years, air trafic dramatically grown in Rwanda, in order to meet the demand, the Governement of Rwanda has decided to upgrade its 3 mains airports. It includes terminal and runway expansions and new security, navigation and meteorological systems.

 

Kigali Kanombe International Airport :

Terminal and Apron expansions (Septembre 2012 – December 2013)

Opening of a Transit Hall

Adding of escalators for disabled people

Check in Desk will be added from 9 to 18

A new conveyor belt will be added (3 in total)

A new car parking will be opened

 

Kamembe International Airport :

New Terminal (2010 – 2012)

New Control Tower (2010 – 2012)

New navigation and meteorological systems

New fire trucks

Extension of the runway (2010 –2014)

From 1500m to 2200m

 

Gisenyi Airport :

Upgrade of the Terminal (2008 –????)

New navigation and meteorological systems

New security scanners

New fire trucks

Works on the runway



Kigali :


 

 

The expansion of the apron is almost completed. Some anti noise barriers were removed. All aircraft parked in front of the terminal must do a push back procedure.

 

 

 

 

19 June 2013

 

 

 


Kigali :


 

 

Prof Silas Lwakabamba (with the sunglass) is talking with the different actors of the project.

 

 

 

 

19 June 2013

 

 

 


Kigali :


 

 

Inside of the new part of the arrival hall.

 

 

 

 

19 June 2013

 

 

 


Kigali :


 

 

The expansion of the arrival hall is on course

 

 

 

 

19 June 2013

 

 


Kigali :


 

 

The number of the check in desk wil be of 15 instead of 8

 

 

 

 

19 June 2013