Rwanda Transport Sector Bulletin 2014/15 : Bugesera Airport Project Status (June 2015)
25/02/2016
Note, from MINIFRA:
Transport Sector Wide Approach (t-SWAp) takes the pleasure to welcome you to this information sharing platform. The platform is the fulfillment of the Joint Sector Review (JSR) recommendations held on 5th June 2015 at MININFRA to the sector to improve on information sharing and updates with all stake holders.
To construct new international airport at Bugesera has been on-going for some time; the government has acquired the site and expropriation exercise has been attained at 95%; the architectural design work has been completed and the efforts to mobilise investors are close to completion.
Here is an overview of Bugesera Airport Project status, for 2014/15 Fiscal year.
Goals :
Land acquisition and Establishment of permanent boundary
Enhanced capability of Airports Planning and Engineering Personnel to Manage Airports Infrastructure Development Projects including,
Results
Overall expropriation is estimated at 98%,
Total amount paid to beneficiaries is 11,686,323,087Rwf,
Cleared files pending in MININFRA is equivalent to 592,807,238Rwf,
The remaining 24,283,640Rwf is for 6 files regards those who refused to sign claiming unfair valuation and 2 others who declined to sign due to insignificant amount,
Establishment of the Permanent Boundary Beacon has been finalized and trainings for Planning and Engineering Personnel on-going,
A découvrir aussi
- No damages on the Gisenyi Airport (Rwanda), but avoid non essential journeys along the border.
- Kigali Airport is a nightmare according to RwandAir’s CEO
- Rwanda hosts the first East African Community tripartite meeting on Airspace Management